Curtains go up near the end of a renovation. The decisions that make them fit have to be made while the ceiling is still open. The track itself usually waits until the curtains are ready to hang.
The order below is for an HDB resale, a condo or a landed house. A new BTO flat follows the same sequence, with a room-by-room list in the BTO curtains checklist. If the flat already has tracks and an old pelmet, start with curtains in a resale renovation.
Curtain track before or after the false ceiling
Fit the track after the false ceiling or curtain box is built.
A track screwed to the bare slab, and then covered by a new ceiling, ends up above the ceiling or at the wrong height. While the ceiling is open, the carpenter builds the curtain box, a recessed pocket, or a timber packer so the track has something solid to fix to. Plasterboard on its own is a poor fixing for a lined curtain. The installation page makes the same point.
The rail goes up with the curtains, after painting, so the track position and the hem are one job. Ceiling track, wall track and rod are compared in the curtain track guide.
If the room is keeping the concrete ceiling and there will be no box, the track can fix to the slab. It is still better installed with the curtains, once you know air-conditioning trunking or a new cornice will not cross that line.
What to lock before the ceiling closes
Settle these while the contractor can still move a wall of gypsum or a cable.
One layer or two. A sheer plus a night curtain needs a deeper box than a single track. Depths are in the pelmet guide. A box built for one track is awkward to widen after it is painted.
Where the curtains stack. The track should run past the frame so the open cloth clears the glass. The track length calculator is a sketch. The cutting length is measured on site.
Whether any window is motorised. A wired motor needs a power point at the end where the motor sits. Agree that end before the electrician works, or the point lands on the wrong side. A battery motor can be added after the ceiling is closed. The motorised guide sets out that choice.
Which rooms are blinds. Kitchens, bathrooms and service yards usually do not get a curtain box. Say so, or the carpenter builds a pelmet over a window that will take a roller blind.
HDB rules that change the box
In an HDB flat the box is carpentry. On HDB’s building works guidelines, “Installation of cornices and pelmet” and “Installation of false ceilings in the flat” are both listed with permit required as No, subject to conditions.
The page says: “For installation of cornices and pelmet, the minimum clearance height of pelmet must be at least 2.10 metres measured from finished floor level.” For false ceilings it states a minimum clearance height of 2.4 metres from finished floor level, not applicable to toilets and bathrooms. Pelmet, false ceiling, cornices and decorative panels must be non-combustible materials. The same page says no gas pipe is to be enclosed in the false ceiling, limits fasteners into the slab, and says flat owners remove and reinstate the pelmet and ceiling for inspection. Those sentences are quoted in full on the pelmet guide.
That is about the box, not the curtain cloth. A low ceiling plus a deep box can miss the 2.10 metre clearance even when the internal depth is enough for two tracks. Other work in the same renovation, such as removing a wall, can still need a permit. Ask the contractor what the submission includes.
Condo and landed houses are outside that HDB table. A condo management office may set the colour seen from outside, and it may restrict balcony fittings. Indoor tracks are covered on the condo curtains page. Landed window walls are on the landed page.
Who runs the cable for a motor
A new power point is electrical work. HDB’s applying for approval page says to engage an EMA-licensed electrical worker for all electrical work. The electrical works guidelines say flats without higher electrical loading require an HDB permit “to install new 15amps power points for air-conditioners or other higher capacity equipment/ appliances.” The same page says other electrical works do not require a permit and remain subject to conditions, and it points to tables for that split. A curtain motor is a small load next to an air-conditioner. The licensed electrical worker should say whether that point is on the permit list or the no-permit list before the ceiling closes. We do not run the wiring.
If the ceiling is already closed, a rechargeable motor avoids a new cable. Ask for the charging port to stay reachable if you still have a say in the box.
When the windows can be measured
Measure after the openings are finished. A floor plan is not a cutting size.
Wait until the frames and grilles are in their final position, the curtain box or pocket is built, and the finished floor level is known. Cloth measured to bare screed sits short once tiles or vinyl go down, and it puddles if the floor is hacked lower. If the contractor will commit to the floor build-up in millimetres and will not change it, the measure can use that figure. If they will not commit, wait.
New windows mean a later measure. Replacing the window is window work. The rental blinds guide cites BCA and HDB on who may do that work in an HDB flat, and on why a bracket is not a reason to drill the casement. Curtain tracks fix to the ceiling, the box or the wall.
What a measure includes is in the measuring guide. A home visit needs a $50 deposit, credited to the order when you buy.
When the curtains are hung
Hang them after painting and after the floor finish, and before sofas and beds block the windows. Dust from hacking marks new cloth, so the curtains should not be in a room that is still being chopped. Bedrooms can be hung first if you are moving in on a fixed date and the living room is still being painted. Tell us that date when you book. Designers use the same timing, described on the trade page.
On the day, check the hem, the overlap past the frame, and that the stack clears the glass. Run a motor a few times before the installer leaves.
If the sequence slips
These are examples of what then has to be worked around.
A single-track box, and a later request for a sheer. The second layer may have to hang in front of the box, or the box is rebuilt.
A motor decided after the ceiling is closed. The practical options are a battery motor, or opening the ceiling again.
A measure taken before the new floor. The hem is short, or it drags.
A track that stops at the window frame. Open curtains cover part of the glass.
Trunking that crosses the track line because it was not marked while the ceiling was open.
Common questions
Should the curtain track go in before or after the false ceiling?
After. While the ceiling is open, build the curtain box or put backing where the track will fix, and run power if a wired motor needs it. Fit the track when the curtains are installed, once the ceiling and the paint are done.
When should curtains be measured during a renovation?
After the window frames, grilles, curtain box and finished floor level are set. Sizes taken from a floor plan change once carpentry and flooring are in.
Does a curtain box in an HDB flat need a renovation permit?
HDB’s building-works guidelines list installation of cornices and pelmet, and installation of false ceilings, as not requiring a permit, if the conditions on that page are met. Those conditions include a pelmet clearance of at least 2.10 metres from the finished floor and non-combustible materials for the pelmet and the false ceiling. Other works in the same renovation can still need a permit. Ask your contractor to check the current page before they build.
Who provides the power point for a motorised curtain?
An EMA-licensed electrical worker, arranged with your contractor. The point needs to be at the motor end of the track before the ceiling or the box is closed. The curtain installer does not run that cable.

BTO Curtains Checklist: What to Plan Before and After Key Collection
Curtain Pelmets and Curtain Boxes in Singapore Homes
Motorised Blinds and Curtains in Singapore: What to Plan Before Renovation