Window treatments in a fit-out are ordered late and drawn early. The blinds go up after the glass is clean and the floor is protected. The recess, the power and the facade colour have to be on the drawings before the ceiling closes.
The commercial page is the list of what we supply for offices, shops, clinics and hotels. This page is where that work sits in the programme. How to write the specification, and what to send for a price, is in how to specify contract curtains.
Early on the drawings, late on site
Before the ceiling and the joinery close, mark four things.
Where a headbox, a recess or a ceiling track has to be. A clinic cubicle track that is only screwed to a ceiling tile will not carry the cloth. The fixer needs the slab, a grid that is braced, or a detail the contractor accepts.
Power for any wired motor, at the end or the head where the motor sits. Battery motors avoid that cable and need a way to recharge. The home version of this choice is in the motorised guide. The same geometry applies on a commercial window.
The colour seen from outside, if the landlord or the mall has a fit-out guide. Many buildings ask for one blind colour on the facade. Send that page with the drawings. We can match a stated colour as closely as the cloth allows, which is also how the office blinds page is written.
Fire performance, if anyone has asked for it. “Fire retardant” on its own is not a fabric. The test name, and what we could and could not find in the Fire Code, is in fire-retardant curtains.
Installation then waits until the openings are finished. Offices, malls and clinics often limit contractor hours, lifts and loading bays. Tell us those rules when you ask for a date. We do not assume every building needs a work permit. Your building management says whether yours does.
Which page to use for each premises
The product choice is already written for each type of space. Use this table to leave this overview and open the page that matches the room.
| Premises | What usually matters | Where to read next |
|---|---|---|
| Office floors and meeting rooms | Glare on screens, a shared colour from outside, blackout only where a projector needs it | Office blinds guide and office blinds |
| Shops, cafes, restaurants | Shopfront sun, a terrace, grease in the kitchen, mall rules on the facade | Shop and F&B blinds |
| Clinics and treatment rooms | Cubicle tracks, a mesh top, laundering, and a separate blind on the street window | Clinic cubicle curtains |
| Hotels and serviced apartments | The same heading and hem in every room, blackout for sleep, cloth that can be cleaned | Hotel curtains |
| Schools, classrooms, halls | Cord safety where children are, blackout for a hall screen, a stage curtain if there is a stage | Blind cord safety, stage curtains, skylight blinds for a glass roof |
| Showflats and sales galleries | A look that matches the renders, measured in the gallery, taken down when the lease ends | Showflat curtains |
A classroom is not an office even when the blind is a roller. Looped cords are a hazard around children. The cord-safety guide is written for homes and applies to the same hardware in a classroom. If the school or the operator has handed you a specification, send it. We have not found a Ministry of Education curtain standard to quote, so we will not invent one.
Partitions that divide a studio, a ward waiting area or a classroom without a wall are a different product from a window blind. Those are on the partition curtains page.
What a fit-out asks for that a home does not
One cloth across a floor, so the building reads as one colour from the street. Split long runs into more than one blind so a team can lower the sunny bays and leave the rest up. That is already in the office guide. Do not copy a domestic package price onto a tower. Commercial jobs are quoted from the measured openings. Hotel guest rooms are quoted per project on the hotel page. Small-office packages, where they apply, are on the office blinds page.
A sample bay before the rest is cut, on a large order. Ask for one window to be made and approved if the floor is big enough that a wrong colour would be expensive to replace. We will say whether a sample bay fits the programme. It is not an automatic free extra.
Access. Measurement and installation may need to be before opening, after the last patient, or over a weekend. Someone on your side has to book the lift and let the installers in. The installation page describes a home visit. The same fixing questions apply, with the building’s rules added.
Who the contract is with. A main contractor, an interior designer, or the tenant can each be the party that orders. Say which, so the quotation goes to the person who will approve it. Designers and contractors can also use the trade page.
Common questions
When should blinds be ordered in a fit-out?
Put the recess, the power and any landlord colour on the drawings before the ceiling closes. Measure after the glass and the partitions are in their final position. Install after the openings are clean, inside the hours the building allows.
Do commercial blinds need a fire certificate?
Sometimes a landlord, an insurer or a tender asks for a named test. A search of the Fire Code text we opened did not find a clause that makes BS 5867 or NFPA 701 mandatory for ordinary office curtains. Read fire-retardant curtains before you write “FR” on a drawing, and ask the project’s qualified person if the building has a specific requirement.
Can one supplier do the office, the clinic rooms and the shopfront?
Often yes, if the specification for each area is attached. Cubicle curtains, outdoor terrace blinds and sunscreen rollers are different products. The commercial page lists them separately so the quote can too.